Steps Involve In Net Metering
Net Metering procedure as per NEPRA’s Regulation along with the timeline. Interconnection of consumer and DISCO and interconnection of DISCO and NEPRA covers in this section.
01
Submission Of Application
Any applicant who meets the requirement of DG as defined in NEPRA’s regulation, submits their application along with the necessary documents to the focal person of the DISCO. Application form is attached at the Annexure and can also be downloaded from NEPRA’s website.
02
Acknowledgement Of Application
The DISCO will acknowledge its receipt and inform the applicant whether the application is completed in all respect or not. For the purpose of net metering connections up to 250 kW capacity, NEPRA has relaxed requirement of inspection from Electric Inspector.
03
Technical Feasibility
As per DISCOs, for connections up to 250 kW, no technical feasibility study is needed. Power Division, Ministry of Energy has directed the DISCOs to carry out technical studies and approve the connections at the Sub-Division level. In case the initial review reveals that the proposed facility is not technically feasible, the DISCO will return the application and communicate the reason to the applicant.
04
Agreement
If the DISCO office is satisfied that the applicant qualifies as a DG, then the DISCO and the applicant will enter into agreement. Agreement form (Schedule-I) is added in the annexure.
05
Generation License
The DISCO office will send the copy of the agreement between the applicant and the DISCO to the NEPRA along with the application for the issuance of Generation license. NEPRA will issue the Generation Licence within seven working days after receipt of requisite documents by DISCOs.
06
Connection Charge Estimate
After the agreement DISCO office will issue the Connection Charge Estimate (CCE), if any, to the applicant for the proposed interconnection facility up to the interconnection point including metering installation.
07
Payment Of CCE
If applicant choose to obtain the meter from concerned DISCO and DISCO has given the notice to the applicant to make the payment of Connection Charge Estimate (CCE), the applicant will pay the same and notify the DISCO office.
08
Installation Of Interconnection Facility
When the charges will be paid the DISCO office will install and commission the proposed interconnection facility after the confirmation of Generation License to the DG by NEPRA.
09
Interconnection Requirements
At the beginning of application procedure DISCO office has to make sure that these initial requirements are to be fulfilled by the applicant.
Procedure For Net Metering Connections
The Power Division, Ministry of Energy (MoE) is promoting net metering and intending to provide the services to the customers at their door step. Therefore, MoE has desired that the installers of systems for net metering (DG installers) as shortlisted by AEDB will be required to process the application for net metering on behalf of consumers applying for net metering connections up to 250 kW capacity. NEPRA has improved/shortened the timeperio for processing net metering applications. Moreover, MoE has asked DISCOs to get applications approved and connections energized within one month of receipt of application from the consumers.